Garage Conversion ADU in Citrus, CA: What It Takes and What It Costs
A garage conversion ADU in Citrus, CA runs $30,000 – $80,000 for the conversion work itself, and $45,000 – $130,000 when the project pulls in the site work, utility upgrades, and finishes a full habitable unit needs. Most conversions we build here take 14 to 20 weeks from permit to final inspection. Call (844) 662-2335 for a free on-site estimate and we’ll walk your actual garage, not a template.
What separates a good conversion from a permitted shed with a bed in it: the unit has to stand on its own for sleeping, cooking, and bathing. That means a real kitchen, a real bathroom, heat, insulation, and a separate address if the city wants one. In Citrus, where a lot of garages sit on sloped foothill ground or attach to 1950s and 1960s ranch homes with shallow slabs, the conversion has to solve for the site before the finishes go in.
How a Garage Conversion ADU Comes Together in Citrus

Here’s the real sequence, with the durations we see on Citrus jobs and what you’ll be deciding at each stage.
Stage 1: Site check and feasibility (1 – 2 weeks)
We measure the garage, check the slab thickness and condition, trace where the water heater, panel, and any gas lines sit, and pull the property’s zoning record to confirm an ADU is allowed on your lot. You decide whether you’re converting the whole garage or keeping a storage bay. On Citrus hillside lots we also look at drainage and grade at the garage door opening, since water running downhill toward a converted garage floor is a common problem here.
Stage 2: Design and permitting (4 – 7 weeks)
We produce the plans, then submit to the city and respond to plan-check comments. You make the big finish decisions here: layout of the kitchen and bath, window placement, and whether the unit gets a separate entry off the alley or the street. Permit timelines in Citrus vary with how complete the plans are, so this is where a design that anticipates the review pays off.
Stage 3: Demo, framing, and rough-in (3 – 4 weeks)
Out comes the old garage door, the storage shelving, any rotted framing, and the old slab if it’s undersized. We frame the new interior walls, cut in windows, and run rough plumbing and electrical for the kitchen and bath. You’ll decide fixture locations now, because moving a drain after rough-in gets expensive. This is also when we trench new utilities out to the sewer or main panel, which on older Citrus properties is where buried citrus-era irrigation piping and old stone walls occasionally turn up.
Stage 4: Insulation, drywall, and systems (3 – 4 weeks)
Insulation goes in, drywall goes up, and the mechanical, electrical, and plumbing systems get their rough inspections. You pick cabinet and counter packages here. We can set you up with brands like KraftMaid and Cambria if you want a known quality tier, or work with what you’ve already chosen.
Stage 5: Finishes and final walkthrough (4 – 5 weeks)
Tile, flooring, paint, cabinets, counters, fixtures, and appliances land in this window. Then comes the final inspection and your walkthrough. If we’ve done our job, the punch list is short and the unit’s ready to rent or hand to family.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Garage Conversion ADU
- Slab-on-grade vs. raised floor. Most Citrus garages have a slab, so staying on it is the cheapest route at $45,000 – $65,000 for the base conversion. If the slab is cracked or the garage sits on a slope, a raised floor or a new slab adds cost but solves drainage.
- Kitchenette vs. full kitchen. A full kitchen with range, sink, and fridge is what makes the unit rentable. A kitchenette saves some money but limits who’ll live there.
- Prefab or stick-built enclosure. Companies like Boxabl and Mighty Buildings make modular units you can drop onto a prepared foundation; we can coordinate with those systems, but they work best when the garage is being torn down and replaced rather than converted.
- Insulation and window grade. The San Gabriel Valley sun is punishing, so we spec higher R-value insulation and dual-pane windows. It adds a few thousand upfront and cuts summer cooling bills.
- Bathroom type. A walk-in shower is easier to fit in a narrow garage footprint than a tub. A tub-to-shower layout keeps the wet area compact.
What a Garage Conversion ADU Costs in Citrus, CA

Plan on $45,000 – $130,000 for a finished garage conversion ADU in Citrus. That headline range is honest but wide, so here’s what moves it.
| Line item | Typical Citrus range |
|---|---|
| Base conversion (demo, framing, drywall, MEP) | $30,000 – $80,000 |
| Full kitchen and bath package | $9,000 – $28,000 |
| Slab repair or new floor | $4,500 – $12,000 |
| Permit fees and inspections | Varies with scope; quote in writing |
| Site work, drainage, entry | $5,000 – $18,000 |
A concrete driveway or apron repair where the old garage door sat is often part of this; see Concrete Driveways & Concrete Work in Citrus.
What pushes the number up: a slab that has to be replaced, moving the panel, running a new sewer line, hillside grading, and finish tier. What keeps it lower: a sound existing slab, existing plumbing and electrical you can tie into, and mid-grade finishes. Every written estimate lists what’s included and what isn’t, so you’re not guessing.
See the difference
Before
After
Before
After
Before
AfterWhat Citrus Homes Do to This Job
Citrus sits in the foothill transition zone, where steep lots and early citrus-era homes create conditions the flat valley cities don’t have. That means garage conversions here often hit slope and drainage problems before they hit finish problems. On a hillside lot, the garage floor may sit below grade at the back, so we spec a new slab and a drainage solution before anything else goes in. Winter rains can push water toward the garage opening, so the entry and apron drainage matter.
Serving Citrus, CA – Our Local Coverage Area
We serve Citrus and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Garage Conversion ADU in Citrus

Most Citrus conversions run 14 to 20 weeks from permit to final inspection, with permitting itself often taking 4 to 7 weeks of that.
Yes. Converting a garage to habitable space requires permits for the structural, electrical, plumbing, and mechanical work, and the unit gets inspected. We pull the permits and pass the inspections. Call (844) 662-2335 for an exact quote.
Often the rough plumbing and panel can stay where they are, which keeps cost down, but the garage door opening has to be closed in and the slab checked. On Citrus properties with older slabs or buried irrigation, we test first and walk you through what’s needed.
Expect $45,000 – $130,000 for the full conversion, with the base work running $30,000 – $80,000 before finishes. Call (844) 662-2335 and we’ll give you a line-item quote.
Every conversion is covered by our 730-Day Done Right Promise. If it’s not done right, we make it right. Our technicians have up to 12 years of experience on this kind of work.
Get a Free Estimate on Your Citrus Garage Conversion ADU
If you own a garage in Citrus and a piece of land around it, you may already be sitting on part of an ADU. Call (844) 662-2335 for a free on-site estimate – we’ll measure the garage, confirm what’s feasible, and put a written range in front of you. A live person answers, 24/7. You’ll get an honest number, a clear timeline, and a crew that shows up in uniform.
Written by the team at Groundwork Construction Co.